Logistics

The entire system is shipped in a single 20" ISO container. To load and unload the container on the pier, a 5t forklift is required. If the ship has no crane to move the winch from the pier on deck, a suitable crane in the port needs to be organized.

The ROV-System can also be shipped in an open top container with hard top. The container is placed on deck and can be loaded/unloaded using a suitable ship crane.

Mobilisation

Mobilisation requires two days. On the first day, ROV and winch are placed and lashed on deck. Further, the control stands and the transformer are installed in the ship´s laboratory. On the second day, the remaining connections and installations are made. This can be done whilst sailing so only one day in port is necessary.

In case no USBL system is available onboard the vessel, the portable IXBLUE USBL System GAPS, that is part of the ROV system, can be installed. The USBL antenna can be either mounted inside the vessel´s moonpool or to a pole on the side of the ship.

Meteor
Installation aboard RV Meteor
Stellung Poseidon
Installation aboard FS Poseidon

Footprint

Once installed on the vessel, the winch remains at its position. The ROV can be moved from its deployment position on the working deck to its parking position using a hand-forklift or a ship crane to make space for other scientific gear that needs to be deployed.

For the installation of the control stands and the transformer, a laboratory large enough and with direct access to the working deck is necessary. The laboratory must have enough space for two pilots and two scientists. On the RV Meteor the control stand is installed inside the "Gross-Nass Labor", on RV Poseidon the "Trockenlabor" is used.

 

 Device Footprint (m) Weight (kg)  Position
 ROV  2.1 x 1.2  1200 Deck 
 Winde  2.1 x 1.9  4700 Deck
 Depressor  0.8 x 0.8  120  Deck 
 Block  1 x 1  100  Deck
 Pliot Flightcase  0.6 x 0.4  35 Control Lab 
 Co-Pilot Flightcase  1 x 0.4  45 Control Lab
 MARUM SCU Flightcase  1 x 0.6  50 Control Lab
 SAAB SCU Flightcase  1.2 x 0.8  150 Control Lab
 Transformer  0.8 x 0.6  500 Control Lab
 Filterbox  0.4 x 0.6  200 Control Lab
FS Poseidon
ROV Squid (in park position) and winch aboard FS Poseidon
Stellung von ROV (in Parkposition) und Winde auf der Ladeluke von FS Meteor. Rechts unten im Bild der Depressor und die Umlenkrolle
ROV Squid (in park position) and the winch on the loading hatch of RV Meteor. The Depressor and the sheave can be seen on the lower right.

Interfacing

To operate the system, the following interfaces and electrical connections are required: 

Unit Specification Connection  
Transformer 380-480VAC/50Hz 4 x 25² to M12 ring terminals 120A fuse protection 
Winch 400VAC/50Hz CEE 5pin (3P+N+PE) 63A fuse protection 
Control stand in the Lab 4 x 220VAC/50Hz CEE 7/4 (grounding receptable) 16A fuse protection (stable grid)
Control stand in the Lab 10-1000MBit Ethernet CAT5 / RJ45  Connection to ship network
USBL System (Posidonia) +5V/0V TTL BNC Connection to Posidonia deck unit

 

Crew / Personnel

Depending on the task of the expedition, ROV-Squid requires a crew of 3-4 pilots/technicians. In addition, 2 cable helpers from the scientific team are needed on deck during deployment and recovery of the system. In case the ROV team consists of 3 members the winch needs to be operated by a scientist or a crew member of the vessel.

During dive operation the pilot is controlling the ROV while the co-pilot is in charge of the navigation and is taking the samples with the manipulator. The third crew member is operating the winch from outside the control lab. If available, the fourth crew member will provide technical support during operation.

The control lab has place for two scientists, that are in charge of the dive. The remaining scientists can join the dive in a different lab on the ship via live videostream and VoIP connection to the control lab.

On the vessel, it has proven to start with the pre-dive check of the system at 6am so it is ready for deployment at 8am. Recovery is between 4pm to 5pm. As soon as the vehicle is on deck, the samples can are recovered and the ROV is being prepared for the next dive by the crew. Depending on the water depth, this results in a bottom time between 5-7 hours. The presented schedule is not mandatory, but can be adjusted to the situation of the ship and expedition.

 Deployment/Recovery

 
 ROV Crew  Science team

 Spotter

 2 x Cable helper
 Pilot  
 Co-Pilot  
 Winch operator  
   

 Dive operation

 
 ROV Crew  Science team
 Pilot  Scientist in charge
 Co-Pilot  Transcript writer
Winch operator  
Support  

 

Operational mode

During dive Operation, the pilot is flying the ROV while the co-pilot is in charge of the navigation and is taking the samples with the manipulator. The third crew member is operating the winch from outside the control lab. If available, the fourth crew member will provide technical support during operation.

The control lab has place for two scientists, that are in charge of the scientific program during the dive. The remaining scientists can join the dive in a different lab on the ship via live videostream and VoIP connection to the control lab.

On the vessel, it has proven to start with the pre-dive check of the system at 6am so it is ready for deployment at 8am. Recovery is between 4pm to 5pm. As soon as the vehicle is on deck, the samples can are recovered and the ROV is being prepared for the next dive by the crew. Depending on the water depth, this results in a bottom time between 5-7 hours. The presented schedule is not mandatory, but can be adjusted to the situation on the ship and expedition.

ROV-Squid is deployed over the side of the vessel. The system has no Tether Management System (TMS) and is deployed in the so called "free flying" or "live boating" mode. First, the ROV is deployed using a ship crane or winch. The pilot is standing on the working deck with the remote console and flies the ROV out on sight. While flying away perpedicular to the ship´s heading, 50m length of the supply cable with floats is payed out manually over the rail. Once this is done, the depressor weight is directly attached to the supply cable. The depressor limits drifting effects on the supply cable by the currents. As soon as the depressor is deployed, the pilot returns to the control lab and continues diving from there. While the ROV is diving to its operational depth, the depressor is lowered in parellel with the ROV winch.